Project Update: December 2019
Work continues on Lee Field, progressing slightly slower than expected due to rain and snow.
The construction of new dugouts will take place throughout the winter, beginning with foundation
work, followed by framing, roofing, brickwork, and electrical work. Concrete was poured in late December for the foundation footings for both Dugout #1 and Dugout #2.
Project Update: January 2020
Both dugout foundations have been installed. A tent-like structure has been built around the dugouts to provide heat for the foundation and masonry wor
k in the coming weeks.
Dugout construction is expected to be completed by the end of February 2020.
Project Update: March 2020
Construction on one dugout is complete and work on the second dugout is slightly ahead of schedule. A stone dust walkway behind the first base dugout is also complete. The field drainage and the scoreboard have been installed, the field has been graded and sod has been laid.
In the coming weeks, the contractor will be installing the remaining fence posts and the mow curb. Once the fencing is complete, the third base bullpen will be installed and the outfield track will be touched up.