Street Resurfacing

SRThe DPW resurfacing program maintains approximately ninety-five (95) miles of “non-connector” streets while funding for the Town's "major connector" streets are addressed as individual capital projects when reconstruction is required.  

The DPW follows a preventative maintenance strategy which slows the deterioration rate of pavement, extends service life and delays cost and disruption of full reconstruction almost indefinitely.  We use chip-seal, Cape Seal and standard hot mix asphalt overlay, or grinding and overlay of the existing road surface in a 10-14 year cycle. Chip-seal is used as an economical treatment where appropriate and grinding is used where there will be a loss of existing curb reveal and/or puddling will occur in driveways or intersecting streets due to an additional overlay.

The DPW targets approximately 10 miles of street from an ongoing evaluation program. This is the optimum amount to minimize repair costs and preserve the roadway system.  The number and mileage of streets is dependent on the combination of treatment types implemented.  The list of streets to be resurfaced are included in a multi-year paving plan with the first year being finalized after post-winter road condition inspections are completed each spring.   

All noted streets are subject to change due to unexpected changes in road condition, utility projects and funding.


Street Resurfacing list 2026

Aberdeen RoadAmherst RoadArnold Road
Barnstable RoadBow StreetChesterton Road
Cliff Road (Garden Rd. to Washington St)Cresent  StreetFairbanks Avenue (Cresent St. to Walnut St.)
Dean RoadDexter RoadEdmunds Road (worcester St. to Lowell Road)
Francis RoadGreat Plain AvenueHampden Street
Kindsbury Street (D'Auria Way to Washington St.)Linden Street (Hollis St. to Everett St.)Linden Street (Pine Tree Road to Wall St.)
Marvin RoadMeadow Brook Rd.Municipal Way (Woodlawn Ave to #30)
Northgate RoadOld Town RoadOttaway Circle
Prospect StreetRichland RoadStearns Road
Sumner RoadWashington St. (Forest St. to Cliff Road)
Whitting Road

Parking Lots 2026

Eaton Court Municipal LotWeston Road Municipal Lot

Street Resurfacing List 2025


Ashmont Road
Completed
Beebe Way
Completed
Burnett Lane
Completed
Cornell Road
Completed
Dearborn Street
Completed
Duxbury Road
Completed
Emerson Road
Completed
Falmouth Circle
Completed
Harrison Avenue
Completed
Lehigh Road
Completed
Lexington Road
Completed

Longmeadow Road
Completed
Maple Road
Completed
Minuteman Lane
Completed
Mount View Road
Completed
Municipal Way
Completed
Old Colony Road
Completed
Paine Street
Completed
Pembroke Road
Completed
Pine Tree Road
Completed
Popular Road
Completed
Schaller Street
Completed
Washburn Avenue
Completed
Webb Avenue
Completed
Whittier Road
Completed
Washington Street @ Upland Road
Crosswalk Replacement
Completed
Washington Street @ #608/#609
Crosswalk Replacement
Completed
Washington Street @ Denton Road
Crosswalk Replacement 
Completed
Washington Street
Sectional renovations between Wellesley Avenue to Church Street
Completed


Additional Roads Completed in 2025

Laurel
Completed
Farm Station Parking Lot
Completed
Spruce Park 
Completed
Squirrel Road
Completed



Street Resurfacing List 2024

Avon Road
Complete
Bay State Road
Complete
Beechwood Terrace
Complete
Berkeley Road
Complete
Berkshire Road
Complete
Brewster Road
Complete
Carlton Road
Complete
Clifford Street
Complete

Cottonwood Road
Complete
Damiel Road
Complete
Dewing Path
Complete
Edmunds Road
Complete
Eliot Street
Complete
Fairbanks Avenue
Complete
Fiske Road
Complete
Forest Street
Complete
Garrison Road
Complete
Harvard Street
Complete
Kipling Road
Complete
Leewood Road
Complete
Middlesex Street
Complete
Nobscot Road
Complete

Pond Road
Complete
Saunders Terrace
Complete
Shirley Road
Complete
Solon Street
Complete
Summit Road
Complete
Swarthmore Road
Complete
Tennyson Road
Complete
Wilson Road
Complete
Woodbine Road
Complete