September 2020 Update: 

Work accomplished on the project to date includes the removal of existing traffic island areas and installation of the storm drainage system.  Scheduled project work for the next two weeks, starting on Monday September 21, 2020, includes: 

  • Beginning of the road lane realignment
  • Installation and relocation of utility conduits
  • Curbing removal and curbing installation to accommodate sidewalks and bike lanes 

Police details will continue to be on site to assist with traffic control through the project work area.